Enforcement actions for erosion and sediment control may be initiated due to which of the following?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Maryland EandS Control Certification Exam. Study with multiple choice questions, flashcards, and explanations for each question. Ace the exam with confidence!

Enforcement actions for erosion and sediment control can indeed be initiated for a variety of reasons related to non-compliance. When construction begins without an approved erosion and sediment control plan, it poses a significant risk to the surrounding environment. An approved plan ensures that appropriate measures are in place to prevent soil erosion and sediment runoff, which can harm water quality and nearby ecosystems.

Working outside the approved limits of disturbance is another critical violation that can lead to enforcement actions. Exceeding these limits can result in increased soil exposure and erosion, making it crucial for regulatory agencies to take steps to mitigate potential environmental damage.

Recurrent minor violations, while they may seem insignificant individually, can accumulate and indicate a pattern of non-compliance that necessitates enforcement. This emphasizes the importance of adherence to regulations and protocols.

Since all these scenarios contribute to improper erosion and sediment control measures, it is valid that enforcement actions can be applied when any of them occur. Hence, the correct answer encompasses all these violations, demonstrating a comprehensive understanding of the enforcement mechanisms in place to safeguard against erosion and sedimentation issues.