What is the minimum requirement for a clear water dike or swale stabilization?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Maryland EandS Control Certification Exam. Study with multiple choice questions, flashcards, and explanations for each question. Ace the exam with confidence!

A clear water dike or swale is essential for directing runoff and minimizing erosion, particularly during construction activities. The minimum stabilization requirement for such structures aims to ensure they effectively manage water flow while preventing sediment from being carried away.

Soil stabilization matting provides a robust approach to stabilization. It not only holds the soil in place, reducing erosion, but also promotes vegetation growth, as it allows for seed germination while protecting the soil underneath. This method is particularly effective in areas where traditional methods may not be sufficient due to steep slopes or heavy rain events.

While options like mulch, seed and mulch, or Class I riprap may offer varying levels of stabilization, they do not meet the defined minimum requirement for a clear water dike or swale stabilization as effectively as soil stabilization matting. Mulch might provide temporary cover but lacks the structural integrity needed for long-term stability. Similarly, seed and mulch help initiate vegetation growth but may not prevent erosion in the short term without additional support. Class I riprap, while durable, is typically used for more permanent and heavy duty erosion control structures rather than a minimum requirement for a dike or swale designed for clear water management. Thus, soil stabilization matting is the correct choice for ensuring the minimum requirement