When should cleanout of a sediment trap or basin be performed?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Maryland EandS Control Certification Exam. Study with multiple choice questions, flashcards, and explanations for each question. Ace the exam with confidence!

The recommended practice for cleanout of a sediment trap or basin is to perform this maintenance when sediment accumulation reaches one-fourth of its storage volume. This guideline is established to ensure that sediment traps and basins remain effective in reducing sediment runoff and maintaining the capacity of the system to manage stormwater. If sediment builds up too much, it can compromise the functionality of the trap or basin, leading to increased erosion and failure to control sedimentation effectively.

Maintaining a cleanout threshold of one-fourth helps to prevent excessive sediment buildup, which could hinder water flow and reduce the basin's capacity to capture additional sediment from subsequent rainfall events. Regular maintenance according to this guideline is essential to ensure ongoing compliance with local regulations and to protect water quality by minimizing sediment discharge into nearby bodies of water.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy